Critical path
Critical path — the sequence of activities in a project network model with the maximum total duration from start to finish; a delay in any activity on the critical path shifts the project completion date. The concept of the critical path underlies network planning methods and schedule calculations, in particular the critical path method (CPM). In R&D and complex engineering programs, the critical path is used to assess timelines, time reserves, and acceleration measures (crashing, fast-tracking)[1][2].
Definition and properties
- The critical path is the longest activity sequence in the network model between the start and end events. Its total duration equals the minimum achievable project duration under the given dependencies[1].
- Activities on the critical path have zero total float; any delay in them shifts project completion[2].
- A project may have several critical paths (for example, when alternative paths are of equal duration, or because of calendars and constraints). Near-critical paths with a small positive float are also distinguished[1].
- The presence of imposed constraints (deadlines, fixed dates) can create negative float, indicating that the current schedule does not satisfy the given constraints[3].
Calculation of early/late dates and floats
The calculation is performed with forward and backward passes through the network (usually in PDM/AON notation).
Forward pass (early dates):
- for start activities: ES = 0 (or the start date per the calendar);
- for each activity j: ESj = the maximum EF of its predecessors;
- EF = ES + d, where d is the activity duration.
Backward pass (late dates):
- for finishing activities: LF equals the early finish of the end event (the overall project duration);
- for each activity j: LS = LF − d; LFj = the minimum LS of all successors[3].
Floats (float/slack):
- Total float (TF): TF = LS − ES = LF − EF — the permissible delay of an activity without shifting the project completion date.
- Free float (FF): FF = the minimum ES of successors − EF — a delay without affecting the early starts of immediate successors[4].
Activities with TF = 0 form the critical path. In the presence of complex dependencies (SS/FF/SF), lags, and calendars, the "longest driving path" criterion is used for robust identification of the critical path, rather than only the "TF = 0" rule[1][2].
Types of dependencies and lags
In PDM, FS (finish-to-start), SS (start-to-start), FF (finish-to-finish), and SF (start-to-finish) dependencies are used, with possible (positive/negative) lags. The presence of lags and different calendars can change the path logic and float estimates; it is recommended to document the calculation rules and use uniform settings in the scheduling software[2][5].
The critical path and resources
The basic definition of the critical path ignores resource constraints. After resource leveling, the structure of the path may change; under resource-constrained conditions, the analysis is complemented by the concept of a "resource-critical path" or the critical chain method[1].
Practical use
- schedule control and "bottlenecks"; focusing management decisions on critical path activities;
- acceleration analysis: crashing (shortening the durations of critical activities at additional cost) and fast-tracking (permitted parallelism), with an assessment of the risks of rework and iterations[2];
- assessing the feasibility of contractual deadlines and identifying contradictions (negative floats, unmanageable constraints);
- building bar charts (Gantt charts) based on the network calculation and regular monitoring of critical path shifts[1].
Historical context
The critical path concept was formulated in the late 1950s as part of the development of the CPM method (DuPont/Remington Rand). The classic 1959 paper laid the foundations of practical planning and critical path calculation; since then the methodology has entered project management standards[6][7][8].
Common mistakes
- Treating the critical path as unique: in practice, several critical or near-critical paths often exist.
- Using only the "TF = 0" criterion without considering the logic of driving relationships, lags, and calendars.
- Losing the critical logic after resource leveling without recalculating the network.
- Relying on fixed dates and hard constraints that hide the true dependencies of the network[1][3].
See also
Links
Literature
- U.S. GAO. Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G). [9]
- PMI. PMBOK® Guide. [10]
- NASA. Systems Engineering Handbook (SP-2016-6105 Rev2). [11]
- Kelley, J. E.; Walker, M. R. (1959). Critical-Path Planning and Scheduling. ACM DL. [12]
- "Critical path method". Wikipedia (en). [13]
- Carnegie Mellon University. Fundamental Scheduling Procedures. [14]
- CSU Pressbooks. Creating an Activity Network Diagram. [15]
- "Precedence diagram method". Wikipedia (en). [16]
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 U.S. Government Accountability Office (GAO). Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G). [1]
- ↑ 2.0 2.1 2.2 2.3 2.4 "Critical path method". Wikipedia (en). [2]
- ↑ 3.0 3.1 3.2 Carnegie Mellon University. Fundamental Scheduling Procedures. [3]
- ↑ Cleveland State University Pressbooks. Creating an Activity Network Diagram. [4]
- ↑ "Precedence diagram method". Wikipedia (en). [5]
- ↑ Kelley, J. E., Jr.; Walker, M. R. (1959). "Critical-Path Planning and Scheduling". IRE-AIEE-ACM '59 (Eastern). ACM Digital Library. [6]
- ↑ Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). [7]
- ↑ NASA. Systems Engineering Handbook (NASA/SP-2016-6105 Rev2). [8]