# Critical path

**Critical path** — the sequence of activities in a project network model with the maximum total duration from start to finish; a delay in any activity on the critical path shifts the project completion date. The concept of the critical path underlies network planning methods and schedule calculations, in particular the [critical path method (CPM)](https://systems-analysis.info/eng/Critical_path_method_(CPM) "Critical path method (CPM)"). In R&D and complex engineering programs, the critical path is used to assess timelines, time reserves, and acceleration measures (*crashing*, *fast-tracking*)<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)[\[2\]](https://systems-analysis.info/eng/Critical_path#cite_note-enwiki-2)</sup>.

## Definition and properties

- The **critical path** is the longest activity sequence in the network model between the start and end events. Its total duration equals the minimum achievable project duration under the given dependencies<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)</sup>.
- Activities on the critical path have zero total float; any delay in them shifts project completion<sup>[\[2\]](https://systems-analysis.info/eng/Critical_path#cite_note-enwiki-2)</sup>.
- A project may have several critical paths (for example, when alternative paths are of equal duration, or because of calendars and constraints). **Near-critical** paths with a small positive float are also distinguished<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)</sup>.
- The presence of imposed constraints (deadlines, fixed dates) can create **negative float**, indicating that the current schedule does not satisfy the given constraints<sup>[\[3\]](https://systems-analysis.info/eng/Critical_path#cite_note-cmu-3)</sup>.

## Calculation of early/late dates and floats

The calculation is performed with forward and backward passes through the network (usually in PDM/AON notation).

**Forward pass** (early dates):

- for start activities: ES = 0 (or the start date per the calendar);
- for each activity j: ES<sub>j</sub> = the maximum EF of its predecessors;
- EF = ES + d, where d is the activity duration.

**Backward pass** (late dates):

- for finishing activities: LF equals the early finish of the end event (the overall project duration);
- for each activity j: LS = LF − d; LF<sub>j</sub> = the minimum LS of all successors<sup>[\[3\]](https://systems-analysis.info/eng/Critical_path#cite_note-cmu-3)</sup>.

**Floats** (float/slack):

- **Total float (TF)**: TF = LS − ES = LF − EF — the permissible delay of an activity without shifting the project completion date.
- **Free float (FF)**: FF = the minimum ES of successors − EF — a delay without affecting the early starts of immediate successors<sup>[\[4\]](https://systems-analysis.info/eng/Critical_path#cite_note-pressbooks-4)</sup>.

Activities with TF = 0 form the critical path. In the presence of complex dependencies (SS/FF/SF), lags, and calendars, the "longest driving path" criterion is used for robust identification of the critical path, rather than only the "TF = 0" rule<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)[\[2\]](https://systems-analysis.info/eng/Critical_path#cite_note-enwiki-2)</sup>.

## Types of dependencies and lags

In PDM, FS (finish-to-start), SS (start-to-start), FF (finish-to-finish), and SF (start-to-finish) dependencies are used, with possible (positive/negative) lags. The presence of lags and different calendars can change the path logic and float estimates; it is recommended to document the calculation rules and use uniform settings in the scheduling software<sup>[\[2\]](https://systems-analysis.info/eng/Critical_path#cite_note-enwiki-2)[\[5\]](https://systems-analysis.info/eng/Critical_path#cite_note-pdm-5)</sup>.

## The critical path and resources

The basic definition of the critical path ignores resource constraints. After resource leveling, the structure of the path may change; under resource-constrained conditions, the analysis is complemented by the concept of a "resource-critical path" or the critical chain method<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)</sup>.

## Practical use

- schedule control and "bottlenecks"; focusing management decisions on critical path activities;
- acceleration analysis: *crashing* (shortening the durations of critical activities at additional cost) and *fast-tracking* (permitted parallelism), with an assessment of the risks of rework and iterations<sup>[\[2\]](https://systems-analysis.info/eng/Critical_path#cite_note-enwiki-2)</sup>;
- assessing the feasibility of contractual deadlines and identifying contradictions (negative floats, unmanageable constraints);
- building bar charts (Gantt charts) based on the network calculation and regular monitoring of critical path shifts<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)</sup>.

## Historical context

The critical path concept was formulated in the late 1950s as part of the development of the CPM method (DuPont/Remington Rand). The classic 1959 paper laid the foundations of practical planning and critical path calculation; since then the methodology has entered project management standards<sup>[\[6\]](https://systems-analysis.info/eng/Critical_path#cite_note-kelley1959-6)[\[7\]](https://systems-analysis.info/eng/Critical_path#cite_note-pmi-7)[\[8\]](https://systems-analysis.info/eng/Critical_path#cite_note-nasa-8)</sup>.

## Common mistakes

- Treating the critical path as unique: in practice, several critical or near-critical paths often exist.
- Using only the "TF = 0" criterion without considering the logic of driving relationships, lags, and calendars.
- Losing the critical logic after resource leveling without recalculating the network.
- Relying on fixed dates and hard constraints that hide the true dependencies of the network<sup>[\[1\]](https://systems-analysis.info/eng/Critical_path#cite_note-gao-1)[\[3\]](https://systems-analysis.info/eng/Critical_path#cite_note-cmu-3)</sup>.

## See also

- [Critical path method (CPM)](https://systems-analysis.info/eng/Critical_path_method_(CPM) "Critical path method (CPM)")
- [PERT method](https://systems-analysis.info/eng/PERT_method "PERT method")

## Links

- <a href="https://systems-analysis.info/wikidata/Critical_path" class="external text" rel="nofollow">Versions of this article in different languages</a>

## Literature

- U.S. GAO. *Schedule Assessment Guide: Best Practices for Project Schedules* (GAO-16-89G). <a href="https://www.gao.gov/products/gao-16-89g" class="external autonumber" rel="nofollow">[9]</a>
- PMI. *PMBOK® Guide*. <a href="https://www.pmi.org/pmbok-guide-standards/foundational/pmbok" class="external autonumber" rel="nofollow">[10]</a>
- NASA. *Systems Engineering Handbook* (SP-2016-6105 Rev2). <a href="https://www.nasa.gov/connect/ebooks/nasa-systems-engineering-handbook/" class="external autonumber" rel="nofollow">[11]</a>
- Kelley, J. E.; Walker, M. R. (1959). *Critical-Path Planning and Scheduling*. *ACM DL*. <a href="https://dl.acm.org/doi/10.1145/1460299.1460318" class="external autonumber" rel="nofollow">[12]</a>
- "Critical path method". *Wikipedia (en)*. <a href="https://en.wikipedia.org/wiki/Critical_path_method" class="external autonumber" rel="nofollow">[13]</a>
- Carnegie Mellon University. *Fundamental Scheduling Procedures*. <a href="https://www.cmu.edu/cee/projects/PMbook/10_Fundamental_Scheduling_Procedures.html" class="external autonumber" rel="nofollow">[14]</a>
- CSU Pressbooks. *Creating an Activity Network Diagram*. <a href="https://pressbooks.ulib.csuohio.edu/project-management-navigating-the-complexity/chapter/7-4-creating-an-activity-network-diagram/" class="external autonumber" rel="nofollow">[15]</a>
- "Precedence diagram method". *Wikipedia (en)*. <a href="https://en.wikipedia.org/wiki/Precedence_diagram_method" class="external autonumber" rel="nofollow">[16]</a>

## References

1.  <span id="cite_note-gao-1">↑ <sup>[1.0](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-0)</sup> <sup>[1.1](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-1)</sup> <sup>[1.2](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-2)</sup> <sup>[1.3](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-3)</sup> <sup>[1.4](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-4)</sup> <sup>[1.5](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-5)</sup> <sup>[1.6](https://systems-analysis.info/eng/Critical_path#cite_ref-gao_1-6)</sup> U.S. Government Accountability Office (GAO). *Schedule Assessment Guide: Best Practices for Project Schedules* (GAO-16-89G). <a href="https://www.gao.gov/products/gao-16-89g" class="external autonumber" rel="nofollow">[1]</a></span>
2.  <span id="cite_note-enwiki-2">↑ <sup>[2.0](https://systems-analysis.info/eng/Critical_path#cite_ref-enwiki_2-0)</sup> <sup>[2.1](https://systems-analysis.info/eng/Critical_path#cite_ref-enwiki_2-1)</sup> <sup>[2.2](https://systems-analysis.info/eng/Critical_path#cite_ref-enwiki_2-2)</sup> <sup>[2.3](https://systems-analysis.info/eng/Critical_path#cite_ref-enwiki_2-3)</sup> <sup>[2.4](https://systems-analysis.info/eng/Critical_path#cite_ref-enwiki_2-4)</sup> "Critical path method". *Wikipedia (en)*. <a href="https://en.wikipedia.org/wiki/Critical_path_method" class="external autonumber" rel="nofollow">[2]</a></span>
3.  <span id="cite_note-cmu-3">↑ <sup>[3.0](https://systems-analysis.info/eng/Critical_path#cite_ref-cmu_3-0)</sup> <sup>[3.1](https://systems-analysis.info/eng/Critical_path#cite_ref-cmu_3-1)</sup> <sup>[3.2](https://systems-analysis.info/eng/Critical_path#cite_ref-cmu_3-2)</sup> Carnegie Mellon University. *Fundamental Scheduling Procedures*. <a href="https://www.cmu.edu/cee/projects/PMbook/10_Fundamental_Scheduling_Procedures.html" class="external autonumber" rel="nofollow">[3]</a></span>
4.  <span id="cite_note-pressbooks-4">[↑](https://systems-analysis.info/eng/Critical_path#cite_ref-pressbooks_4-0) Cleveland State University Pressbooks. *Creating an Activity Network Diagram*. <a href="https://pressbooks.ulib.csuohio.edu/project-management-navigating-the-complexity/chapter/7-4-creating-an-activity-network-diagram/" class="external autonumber" rel="nofollow">[4]</a></span>
5.  <span id="cite_note-pdm-5">[↑](https://systems-analysis.info/eng/Critical_path#cite_ref-pdm_5-0) "Precedence diagram method". *Wikipedia (en)*. <a href="https://en.wikipedia.org/wiki/Precedence_diagram_method" class="external autonumber" rel="nofollow">[5]</a></span>
6.  <span id="cite_note-kelley1959-6">[↑](https://systems-analysis.info/eng/Critical_path#cite_ref-kelley1959_6-0) Kelley, J. E., Jr.; Walker, M. R. (1959). "Critical-Path Planning and Scheduling". *IRE-AIEE-ACM '59 (Eastern)*. *ACM Digital Library*. <a href="https://dl.acm.org/doi/10.1145/1460299.1460318" class="external autonumber" rel="nofollow">[6]</a></span>
7.  <span id="cite_note-pmi-7">[↑](https://systems-analysis.info/eng/Critical_path#cite_ref-pmi_7-0) Project Management Institute. *A Guide to the Project Management Body of Knowledge (PMBOK® Guide)*. <a href="https://www.pmi.org/pmbok-guide-standards/foundational/pmbok" class="external autonumber" rel="nofollow">[7]</a></span>
8.  <span id="cite_note-nasa-8">[↑](https://systems-analysis.info/eng/Critical_path#cite_ref-nasa_8-0) NASA. *Systems Engineering Handbook* (NASA/SP-2016-6105 Rev2). <a href="https://www.nasa.gov/connect/ebooks/nasa-systems-engineering-handbook/" class="external autonumber" rel="nofollow">[8]</a></span>